Dive Brief:

A Maine jury ruled Thursday that Avangrid had the right to build a 145-mile transmission line when state voters in 2021 approved a ballot measure that interrupted construction of the New England Clean Energy Connect, NECEC, project.

The 9-0 decision in the Maine Business and Consumer Court in Portland turns aside the referendum and allows work to resume on the $1 billion project to deliver Canadian hydropower to the New England grid. Massachusetts ratepayers would be the primary beneficiaries and bear the costs.

  • Backers of the project say the transmission line through western Maine will combat climate change by supplying up to 1,200 MW of hydropower,…