Power grid delays challenge Amazon's data center expansion in Europe
channelnewsasia.com·1d
🏢Data Centers
Preview
Report Post

BRUSSELS, Feb 3 : Long delays to get power grid connections are challenging Amazon’s plans to expand data centers in Europe, the company told Reuters, as industries ramp up pressure on policymakers to upgrade ageing energy grids.

Energy-intensive industries have urged the European Union to invest more in grids, warning that a fast connection to stable, reliable power networks is a key criteria for investments in new industrial sites in Europe.

Pamela MacDougall, Amazon Web Services’ (AWS) head of energy markets and regulation in EMEA, said the timeline for getting a grid connection had become one of the biggest deciding factors in the company’s data center investments.

Connecting to the transmission network in Europe can take up to seven years - versus the roughly two years it can …

Similar Posts

Loading similar posts...

Keyboard Shortcuts

Navigation
Next / previous item
j/k
Open post
oorEnter
Preview post
v
Post Actions
Love post
a
Like post
l
Dislike post
d
Undo reaction
u
Recommendations
Add interest / feed
Enter
Not interested
x
Go to
Home
gh
Interests
gi
Feeds
gf
Likes
gl
History
gy
Changelog
gc
Settings
gs
Browse
gb
Search
/
General
Show this help
?
Submit feedback
!
Close modal / unfocus
Esc

Press ? anytime to show this help